Break Water & Rock Revetment

ICAD 4 SWRO 2M USGPD- Installation of Intake, Outfall Pipeline and Breakwater

Location :

ICAD 4, Abu Dhabi

Client :

Corodex Industries LLC

Year :

2023

Construction of (482m long) Rock Revetment Works

Location :

Al MIRFA, Abu Dhabi

Client :

Sheikh Suroor Private Office

Year :

2022

Design and Construction of Naval Jetty and Breakwater

Location :

Sir, Bu Nayr, Abu Dhabi

Client :

Command of Military Works UAE Armed Forces

Year :

2020

Complete the work of repair of (2) breakwaters damage for the benefit of the armed forces

Location :

Lusail, QATAR

Client :

Al Huda Engineering Works

Year :

2020

Construction of Break Water Marina & Dredging works

Location :

Assab, Eritrea

Client :

UAE Armed Forces Command of Military Works

Year :

2019

Construction of Breakwaters for 260 & 120 LM

Location :

Mina Zayed Port, Abu Dhabi

Client :

UAE Armed Forces, Directorate Of Military Works, Abu Dhabi, U.A.E

Year :

2008

Beach Renovation Works

Location :

H.H. Sheikh Haza’a island, Musafah Palace, Abu Dhabi, U.A.E

Client :

Capriole General Construction Company

Year :

2008

Construction Of Breakwaters, Sheet Pile Jetty for Zayed Port Construction Department

Location :

Zayed, Port, ABU DHABI, UAE

Client :

UAE Armed Forces, Directorate Of Military Works

Year :

2008

Construction Of Breakwaters, Sheet Pile Jetty

Location :

Zayed Port Construction Department, Abu Dhabi

Client :

UAE Armed Forces, Directorate Of Military Works

Year :

2008

Breakwater Construction of 75 LM of two (2) Breakwater & Beach Setting

Location :

Al Ghuslan Island, Abu Dhabi, U.A.E,

Client :

Capriole General Construction Company

Year :

2007

Breakwater Construction of 20 LM Breakwater Extra @ Al Ghuslan Island

Location :

Abu Dhabi, U.A.E

Client :

Capriole General Construction Company

Year :

2007

Construction of Rock Revetment Protection for 686 LM

Location :

Zayed port, Head Quarter of Coast Guards, ABU DHABI, UAE

Client :

UAE Armed Forces, Directorate Of Military Works, Abu Dhabi, U.A.E

Year :

2007

Construction Of Rock Revetment for 220 LM for Armed Forces

Location :

ABU DHABI, UAE

Client :

UAE Armed Forces, Directorate Of Military Works, Abu Dhabi, U.A.E

Year :

2007

Construction of Breakwaters for 200 & 140 LM for Armed Forces

Location :

ABU DHABI, UAE

Client :

UAE Armed Forces, Directorate Of Military Works, Abu Dhabi, U.A.E

Year :

2007

Construction of Rock Protection for 1,250m

Location :

H.H. Sheikh Mansour Bin Zayed, Abu Dhabi, U.A.E

Client :

H.H. Sheikh Mansour Bin Zayed Al Nahyan Private Office

Year :

2007

Beach Works @ Private Island

Location :

Delma Island Airport, ABU DHABI, UAE

Client :

UAE Armed Forces, Directorate Of Military Works, Abu Dhabi, U.A.E

Year :

2004

Construction Of Breakwater, Rock Protection, sheet Piling Works, Dredging and Jetty at Coastal Guards Head Quarter

Location :

ABU DHABI, UAE

Client :

UAE Armed Forces, Directorate Of Military Works, Abu Dhabi, U.A.E

Year :

2007

Construction Of Two (2) Breakwater 75LM & Beach Setting

Location :

Al Ghuslan Island, Abu Dhabi, U.A.E

Client :

Capriole General Construction Company

Year :

2007

Construction of 20 LM Breakwater Extra

Location :

Al Ghuslan Island, Abu Dhabi, U.A.E

Client :

Capriole General Construction Company

Year :

2007

Construction Of Breakwaters and Rock Revetment

Location :

Gantooth Area, ABU DHABI, UAE

Client :

H.H. Sheikh Mansour Bin Zayed Al Nahyan Private Office

Year :

2005

Construction of Breakwater & Jetty

Location :

Gaga Island, ABU DHABI, UAE

Client :

UAE Armed Forces, Directorate Of Military Works, Abu Dhabi, U.A.E

Year :

2005

Construction of Breakwater & Jetty

Location :

Delma Island, ABU DHABI, UAE

Client :

UAE Armed Forces, Directorate Of Military Works, Abu Dhabi, U.A.E

Year :

2005

Construction Of Rock Revetment For Road to Ras Gumais Base – Phase II

Location :

ABU DHABI, UAE

Client :

UAE Armed Forces, Directorate Of Military Works, Abu Dhabi, U.A.E

Year :

2005

Marina & Rock revetment Works @ Private Island,

Location :

H.H. Sheikh Mansour Bin Zayed, Abu Dhabi, U.A.E

Client :

H.H. Sheikh Mansour Bin Zayed Al Nahyan Private Office

Year :

2004

Construction of Breakwater

Location :

Private Island for H.H. Sheikh Mansour Bin Zayed, Abu Dhabi, U.A.E

Client :

H.H. Sheikh Mansour Bin Zayed Al Nahyan Private Office

Year :

2004

Construction of Rock Revetment

Location :

Private Island for H.H. Sheikh Mansour Bin Zayed, Abu Dhabi

Client :

H.H. Sheikh Mansour Bin Zayed Al Nahyan Private Office

Year :

2004

Construction of Breakwater For Coast Guards

Location :

Ghantoot, ABU DHABI, UAE, U.A.E

Client :

UAE Armed Forces, Directorate Of Military Works, Abu Dhabi, U.A.E

Year :

2004

Construction of Breakwater For H.Q. Border Guards

Location :

Mina Zayed Phase II, ABU DHABI, UAE

Client :

UAE Armed Forces, Directorate Of Military Works, Abu Dhabi, U.A.E

Year :

2004

Construction of Breakwaters and Marine Amenities

Location :

Ras Gumais Naval base Phase I, ABU DHABI, UAE

Client :

UAE Armed Forces, Directorate Of Military Works, Abu Dhabi, U.A.E

Year :

2004